ENTSOG & ENTSO-E Ten year network development plan: What the numbers say about EU’s deployment pace
Europe’s energy transition requires a different generation mix. But is capacity being deployed fast enough to get there? Our analysis suggests that solar PV, BESS, and coal retirements are broadly on track with the pace implied by the TYNDP 2026 capacity targets. Wind shows the largest gap between recent deployment and future requirements. On the other hand, recent gas developments appear to be moving in the opposite direction of the scenario’s decommissioning pathway. Article by Berk Noyan, July 2026.
In June 2026, ENTSO-E and ENTSOG published the draft Ten-Year Network Development Plan (TYNDP) 2026, the joint long-term outlook underpinning European electricity and gas/hydrogen infrastructure planning. The report contains a wide range of assumptions on Europe’s future energy system. In this article, however, we focus on one specific question: not how much capacity Europe will have by 2030 or 2050, but how fast it would need to be built to get there.
National Trends+ as the central scenario
The TYNDP 2026 central scenario is called National Trends+.
This baseline is a bottom-up scenario based on national policies and updated NECPs, aimed at closing the remaining gaps to the EU’s 2030 energy and climate targets and the 2050 climate neutrality objective. If the combined national plans do not collectively meet the EU-wide targets, the remaining gaps are filled by reducing final energy consumption, prioritizing the replacement of the most carbon-intensive fuels.
Why annual pace matters
ENTSOG presents its TYNDP scenario as installed capacity milestones for 2030, 2035, 2040, and 2050. While these end-state targets are useful, they hide an equally important dimension. Every capacity milestone implicitly defines periodic average annual deployment rates required to reach it.
Historical pace versus required pace
To quantify the implied deployment pace, we calculated average annual net capacity additions for 2020–2025 and derived annual deployment rates for subsequent years by interpolating between the National Trends+ capacity milestones.
Last year’s addition (56 GW) almost matches the pace of 57 GW/yr needed through 2030, which is encouraging. However, several factors could make it difficult to sustain this pace:
Solar PV
• Falling capture price: Solar output floods the market at midday, pushing prices down and sometimes negative. Some governments are pulling back support for those negative midday hours specifically, weakening returns further.
• Grid congestion: Limits further deployment and increases curtailment.
• Replacement need: Ageing panels will need replacing over the next decade. Gross installation volumes, and pressure on the panel and inverter supply chain, will need to run higher than the net numbers alone suggest.
Wind
This is where the gap between recent history and required pace is widest. The deployment rates required through 2030 (30.6 GW/yr) and 2035 (43.8 GW/yr) are more than double and triple, respectively, to the average pace of 13.2 GW/yr observed over the past five years. No single cause explains it:
• Slow permitting, long grid connection queues, thin margins for turbine makers, and undersubscribed offshore auctions have all held the sector back in recent years.
• As is the case with solar generation, wind power will also face the replacement of ageing assets. However, since wind capacity has not expanded as rapidly as solar PV in recent years, the replacement cycle is likely to be more gradual and spread over a longer period.
Wind’s role in the scenario matters. Unlike solar, it keeps producing through the night and winter, and offshore wind especially has a higher capacity factor. Closing this gap is critical since solar alone cannot compensate for wind underdelivery.

Natural gas
The story here runs against the scenario’s own logic. Even though decommissioning is assumed to go forward, EU gas capacity actually grew over the past five years with a pace of 1.8 GW/yr. Germany, for example, plans to procure around 10-12 GW of new gas-fired capacity. These plants will transition to hydrogen later on1. While intended to support security of supply during the transition, such investments point to near-term gas capacity growth rather than the reductions implied by the scenario.
Coal
A rare bit of good news. Retirement has tracked close to the required pace. The average decommissioning rate of 7.2 GW/yr over the last five years is approaching the 11.6 GW/yr reduction in capacity required through 2030. Many countries have already shut down their remaining coal plants, and most others have set clear phase out dates. Coal is in a better position than natural gas plants relative to its target.
BESS
Deployment has been accelerating, with the 27 GW installed last year nearly doubling the average pace of 14.2 GW/yr observed between 2020 and 2025. As more renewables connect to the grid, battery storage becomes more valuable for managing that variability. Grid connection reforms and co-located storage plus generation projects should help keep this momentum going. Until the end of the analyzed period, replacement volume requirements are limited.
Hydrogen turbines: The scenario does not rely on hydrogen-fired generation in the near term. Most deployment is concentrated in the second half of the 2030s and peaking at 10 GW/yr between 2035 and 2040. This reflects the industry’s expectation that hydrogen power will only scale once fuel supply and infrastructure mature, and costs decline.
Nuclear: Similar to hydrogen turbines, nuclear plays only a limited role in the scenario over the next decade. Capacity additions remain close to zero through 2030 and accelerate mainly between 2035 and 2040, reaching 4.6 GW/yr. This aligns with a common industry view: while interest in new nuclear and SMRs is growing, long development timelines mean any meaningful contribution is likely to come only in the second half of the 2030s.
Not the Target, but the Pace
The gap between recent trends and required pace varies by technology as well as the upcoming replacement volume growth. Looking only at capacity targets can hide the scale of the effort required to reach them. In particular, as replacement needs begin to grow. The key question is not the end-state itself, but how far current deployment trends are from the pace needed to achieve it.
From Scenarios to Market Impact
This analysis is not a judgment on whether National Trends+ is achievable. Rather, it highlights where reality and the scenario diverge most, which is often where risks and opportunities emerge for market participants. At KYOS, fundamental market models are used to translate these scenarios into impacts on power prices, asset value, and portfolio performance, helping clients assess alternative pathways and their implications.
Let us know if we can help you with your fundamental curves or other projects!